Transport of floating foundations for offshore wind turbines
On the evening of Friday, June 5, 2026, the first module rolled out of Welcon’s factory in Give. It was part of Stiesdal Offshore’s TetraSub foundation – a floating foundation for the offshore wind turbines of the future and the largest and most complex project in Welcon’s history. Our task was to get the modules safely through the Central Jutland landscape and to the quay in Hvide Sande.
The task
Each element weighed up to approx. 550 tonnes, and such large items cannot simply be driven out onto the road. The transports had to be carried out at night and in stages, one module at a time. Before the first module left Give, we had therefore spent a long time preparing the route together with our partners and in close dialogue with the Danish Road Directorate, which was both accommodating and solution-oriented.
A few thousand horsepower through the night
On the night of June 6, the first module drove through the countryside – with a couple of thousand horsepower and so many wheels that we almost gave up counting them. Curious people stood along the route and followed, and TV MIDTVEST covered the journey. On the night of June 7, module 1 arrived in Hvide Sande, and module 2 was already on its way. A single generator gave up along the way, but we were quickly up and running again, and the rest went according to plan. One rule applied the whole way: safety comes before everything else.
Onward to Portugal
On June 29th, the components were loaded onto the ship MV Hilke in Hvide Sande, heading for Portugal. Our film from the first part of the project has been viewed more than 112,000 times. On August 12th, we were back in Give – this time with 4 heavy tractor units, 130 THP axle lines and 20 escort vehicles.
Thanks to Welcon, Stiesdal Offshore, Stendevad Følgebiler, Terranor and the Danish Road Directorate for a really good collaboration.